Spotting extra work early

Is this change request extra work?

Extra work creeps into a project through small requests: one more screen, one more report. If you only raise it at the end, you face a difficult conversation. AI can set a change request against the agreed scope and show the effect on time, cost and acceptance.

How do you start with one request?

Suppose the customer asks in a meeting whether the new portal could also be in English. Give AI the signed proposal, the scope agreements, your change criteria and the schedule. Ask for a comparison sheet.

Fictional example

Change request: English version of the portal

In scope?
No. The proposal only mentions a Dutch-language portal.
Effect
About twelve days of extra work for translation and testing. The end date moves by two weeks, unless an extra colleague joins.
Acceptance
The English text has to be supplied or approved by the customer. Who will do that?

From request to agreement

The project manager presents the sheet to the customer: do it now, with more time and cost, or after go-live as a separate piece of work.

An English version is perfectly doable, but it falls outside what we agreed. Would you like it now, with these consequences, or after go-live?

The project manager confirms the estimate with the team. Prices and new agreements go through the agreed approval route.

In an AI Work Session for teams, you assess a few fictional change requests together. After half a day, your team knows which criteria it applies.

How does the whole team get this right?

Spotting extra work works when everyone knows exactly what was agreed and when a request is a change. Record the scope agreements, the change criteria and who can approve.

With AI Workplace Start, we set up assessment around those agreements. Every project manager then handles a change request in the same way.

See how AI Workplace Start supports this way of working

What work can an AI assistant take on?

An assistant can spot requests in meeting notes and customer emails that fall outside the scope, and prepare a comparison sheet.

The project manager decides whether to discuss the request with the customer.

How does this become part of the project week?

Agree when a request is recorded as a change, who estimates the consequences and who approves.

  • Recorded. How many changes were recorded before the work was done?
  • Invoiced. What share of the extra work was actually invoiced?
  • Margin. How does margin differ between projects with and without recorded changes?

Extra work isn’t the problem. Extra work nobody agreed is.

When does a system of your own pay off?

Do many work packages and contract versions need checking against each other automatically? Then spotting extra work needs an integration of your own.

With Custom AI, Sachs AI first looks at whether a solution of your own is worth the investment. We help you choose a development partner and can manage the build.